PJM-AH2-013
15.996 MW hybrid in Cumberland, VA · In queue since October 2021 · Proposed COD December 2022
15.996 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 2m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
PJM-AH2-013 is a proposed 16.0 MW hybrid solar and battery project located in Cumberland County, Virginia. The project, which consists of 16.0 MW of solar generation, is in the PJM interconnection queue as of October 12, 2021, with a proposed commercial operation date of December 31, 2022. Dominion is the interconnecting utility.
The interconnection agreement for PJM-AH2-013 is currently listed as "In Progress (unknown study)". The point of interconnection is the Cartersville 34.5 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Cartersville 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-013