PJM-AH2-021
150 MW hybrid in Barren, KY · In queue since October 2021 · Proposed COD November 2026
150 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-13
PJM-AH2-021 is a proposed 150 MW hybrid solar and battery project located in Barren County, Kentucky. The project, which consists of 150 MW of solar generation, is in the PJM interconnection queue as of October 27, 2021, with a proposed commercial operation date of November 13, 2026. The interconnecting utility is EKPC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Summer Shade - Barren County 161 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
Barren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Summer Shade - Barren County 161 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-021