PJM-AH2-030
90 MW generation in Jefferson, WV · In queue since November 2021 · Proposed COD June 2025
90 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
PJM-AH2-030 is a proposed 90 MW solar generation project located in Jefferson County, West Virginia. The project, which interconnects to the APS utility via the Feagan's Mill 138 kV point of interconnection, entered the PJM interconnection queue on November 3, 2021. Its proposed commercial operation date is June 1, 2025.
The interconnection agreement for PJM-AH2-030 is currently listed as "In Progress (unknown study)". The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
WV
County
Jefferson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Feagan's Mill 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MECHATWN34.5 KV BLAKESP
- POI Substation
- Feagan's Mill Substation