PJM-AH2-035
100 MW storage in Prince William, VA · In queue since November 2021 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PJM-AH2-035 is a proposed 100 MW battery storage project located in Prince William County, Virginia. The project, which consists of a single 100 MW battery component, is being developed within the Dominion service area.
The project is listed in the PJM interconnection queue with an entry date of November 9, 2021, and a proposed commercial operation date of December 31, 2028. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Possum Point 500kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Prince William
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Possum Point 500kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- POSSUMP414 KV G3
- POI Substation
- Possum Point Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-035