PJM-AH2-038
10.75 MW generation in Hancock, WV · In queue since November 2021 · Proposed COD December 2024
10.75 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH2-038 is a proposed solar generation project with a total capacity of 10.75 MW. The project is located in Hancock County, West Virginia, and is interconnected within the PJM Interconnection queue. The queue entry date is November 13, 2021, with a proposed commercial operation date of December 31, 2024. The interconnecting utility is APS.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Weirton - Arroyo 25 kV line.
Generated from interconnection queue and public data sources
State
WV
County
Hancock
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Weirton - Arroyo 25 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-038