PJM-AH2-042
5.75 MW generation in Berkeley, WV · In queue since November 2021 · Proposed COD December 2024
5.75 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH2-042 is a proposed solar generation project with a total capacity of 5.75 MW. The project is located in Berkeley County, West Virginia, and interconnects to the PJM grid via the Marlowe - North Martinsburg 34.5 kV point of interconnection. The project entered the PJM interconnection queue on November 13, 2021, with a proposed commercial operation date of December 31, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project is being developed within the service territory of APS. The interconnection queue entry identifies the project as consisting of 5.75 MW of solar generation. The project's status within the PJM interconnection queue is listed as active.
Generated from interconnection queue and public data sources
State
WV
County
Berkeley
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Marlowe - North Martinsburg 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-042