PJM-AH2-049
20 MW storage in Somerset, MD · In queue since December 2021 · Proposed COD June 2025
20 MW
Capacity
1
Components
Battery
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-02
PJM-AH2-049 is a proposed 20 MW battery storage project located in Somerset County, Maryland. The project is interconnected to the PJM grid via the Delmarva Power & Light (DPL) utility, with the point of interconnection at the Crisfield 69kV substation.
The project entered the PJM interconnection queue on December 20, 2021, and has a proposed commercial operation date of June 2, 2025. Its interconnection agreement status is listed as "In Progress (unknown study)". The developer is unknown.
Generated from interconnection queue and public data sources
State
MD
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Crisfield 69kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CRISFIE 4 KV G1
- POI Substation
- Crisfield Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.