PJM-AH2-052
1.98 MW generation in Allegany, MD · In queue since December 2021 · Proposed COD December 2022
1.98 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1 year
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-02
PJM-AH2-052 is a proposed solar generation project with a total capacity of 1.98 MW, located in Allegany County, Maryland. The project is interconnected to the Delmarva Power & Light (DPL) grid at the New Hope 12.47 kV point of interconnection. It entered the PJM interconnection queue on December 21, 2021, with a proposed commercial operation date of December 2, 2022. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists solely of solar photovoltaic generation, with the full 1.98 MW capacity attributed to this technology. The project's status within the PJM queue is listed as active.
Generated from interconnection queue and public data sources
State
MD
County
Allegany
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
New Hope 12.47 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NEWHOPE 69 KV N-HOPE
- POI Substation
- New Hope Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-052