PJM-AH2-054
1.98 MW generation in Wicomico, MD · In queue since December 2021 · Proposed COD December 2022
1.98 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1 year
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-02
PJM-AH2-054 is a proposed solar generation project with a total capacity of 1.98 MW. The project is located in Wicomico County, Maryland, and is interconnected within the PJM Interconnection region, with Delmarva Power & Light (DPL) as the utility. The project entered the PJM queue on December 21, 2021, and originally proposed a commercial operation date of December 2, 2022.
The interconnection status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Edgewood 12.47 kV I.
Generated from interconnection queue and public data sources
State
MD
County
Wicomico
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Edgewood 12.47 kV I
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM