PJM-AH2-057
29.9 MW generation in Buckingham, VA · In queue since December 2021 · Proposed COD December 2025
29.9 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4 years
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
PJM-AH2-057 is a proposed solar generation project with a total capacity of 29.9 MW. The project is located in Buckingham County, Virginia, and is interconnected within the PJM Interconnection queue. The queue entry date is December 23, 2021, with a proposed commercial operation date of December 1, 2025. The interconnection agreement status is currently "In Progress (unknown study)". The designated point of interconnection (POI) is the Scottsville - CVEC Delivery Point at 46 kV.
The project developer is unknown, and the interconnecting utility is AEP. The project consists solely of solar generation, with a total solar capacity of 29.9 MW. There is no match to an existing operating plant in the EIA database, and there is no indication of recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Buckingham
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Scottsville - CVEC Delivery Point 46 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WOODSDP 115 KV TX1
- POI Substation
- Woods Delivery Point
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-057