PJM-AH2-060
55 MW storage in Prince William, VA · In queue since December 2021 · Proposed COD December 2027
55 MW
Capacity
1
Components
Battery
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
6 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
PJM-AH2-060 is a proposed 55 MW battery storage project located in Prince William County, Virginia. The project is being developed within the Dominion service area and has an interconnection point at the Possum Point 230 kV substation.
The project is listed in the PJM interconnection queue with an entry date of December 24, 2021, and a proposed commercial operation date of December 1, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Prince William
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Possum Point 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- POSSUMP414 KV G3
- POI Substation
- Possum Point Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.