PJM-AH2-062
5 MW generation in Chester, PA · In queue since December 2021 · Proposed COD May 2023
5 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 5m
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-01
PJM-AH2-062 is a proposed solar generation project located in Chester County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 5 MW, consists of a single 5 MW solar component. Its interconnection request was entered into the PJM queue on December 31, 2021, with a proposed commercial operation date of May 1, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is located within the PECO utility service area. The point of interconnection is designated as "TBD 34kV". The project's status is currently listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Chester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PECO
Entity
PJM
Service Type
—
Point of Interconnection
TBD 34kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-062