Project PJM-AH2-062 — Project Summary

Queue ID
PJM-AH2-062
Capacity
5 MW
Technology
Solar
Status
active
Location
Chester, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH2-062

PJM-AH2-062BetaActiveSolarPJMLBNL + Live

5 MW generation in Chester, PA · In queue since December 2021 · Proposed COD May 2023

5 MW

Capacity

1

Components

Solar

4y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection

Total Duration

1y 5m

Schedule

37 months past proposed COD

In Study38%
Queue EntryDec 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-05-01

About

PJM-AH2-062 is a proposed solar generation project located in Chester County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 5 MW, consists of a single 5 MW solar component. Its interconnection request was entered into the PJM queue on December 31, 2021, with a proposed commercial operation date of May 1, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".

The proposed project is located within the PECO utility service area. The point of interconnection is designated as "TBD 34kV". The project's status is currently listed as active within the PJM interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

PA

County

Chester

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

PECO

Entity

PJM

Service Type

Point of Interconnection

TBD 34kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH2-062