PJM-AH2-063
20 MW generation in Beaver, PA · In queue since December 2021 · Proposed COD December 2023
20 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2 years
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AH2-063 is a proposed 20 MW solar generation project located in Beaver County, Pennsylvania. The project is in the PJM interconnection queue as of December 30, 2021, with a proposed commercial operation date of December 31, 2023. The interconnection agreement is currently listed as "In Progress (unknown study)".
The proposed project, which will interconnect with Duquesne Light (DL) at the North Ramsey 23 kV point of interconnection, is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Beaver
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DL
Entity
PJM
Service Type
—
Point of Interconnection
North Ramsey 23 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-063