PJM-AH2-064
10 MW generation in Beaver, PA · In queue since December 2021 · Proposed COD December 2023
10 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2 years
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AH2-064 is a proposed solar generation project located in Beaver County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 10 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is the South Ramsey 23 kV substation.
The project entered the PJM interconnection queue on December 31, 2021, with a proposed commercial operation date of December 31, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
Beaver
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DL
Entity
PJM
Service Type
—
Point of Interconnection
South Ramsey 23 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-064