Project PJM-AH2-068 — Project Summary

Queue ID
PJM-AH2-068
Capacity
100 MW
Technology
Solar
Status
active
Location
Wood, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH2-068

PJM-AH2-068BetaActiveSolarPJMLBNL + Live

100 MW generation in Wood, OH · In queue since January 2022 · Proposed COD December 2027

100 MW

Capacity

1

Components

Solar

4y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection

Total Duration

5y 11m

In Study38%
Queue EntryJan 13, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

About

PJM-AH2-068 is a proposed 100 MW solar generation project located in Wood County, Ohio. The project, which interconnects to the Pemberville - West End Fostoria 69 kV point of interconnection, entered the PJM interconnection queue on January 13, 2022. The listed utility is AEP.

The proposed commercial operation date for PJM-AH2-068 is December 31, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)".

Generated from interconnection queue and public data sources

Project Details

State

OH

County

Wood

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Pemberville - West End Fostoria 69 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH2-068