PJM-AH2-069
250 MW generation in Wythe, VA · In queue since January 2022 · Proposed COD May 2025
250 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-30
PJM-AH2-069 is a proposed solar generation project located in Wythe County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 250 MW, consists entirely of solar photovoltaic generation. The queue entry date for PJM-AH2-069 is January 13, 2022, with a proposed commercial operation date of May 30, 2025.
The interconnection status for PJM-AH2-069 is listed as "In Progress (unknown study)". The point of interconnection is the Jackson Ferry - Progress Park 138 kV line, and the interconnecting utility is AEP. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
Wythe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
JAckson Ferry - Progress Park 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-069