PJM-AH2-070
1.98 MW generation in Wicomico, MD · In queue since January 2022 · Proposed COD January 2023
1.98 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1 year
Schedule
40 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-01-27
PJM-AH2-070 is a proposed solar generation project with a total capacity of 1.98 MW. The project is located in Wicomico County, Maryland, and is interconnected within the PJM Interconnection queue. The queue entry date is January 19, 2022, with a proposed commercial operation date of January 27, 2023.
The interconnection agreement (IA) status for PJM-AH2-070 is listed as "In Progress (unknown study)". The designated point of interconnection (POI) is Edgewood 12.47 kV II, and the interconnecting utility is DPL.
Generated from interconnection queue and public data sources
State
MD
County
Wicomico
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Edgewood 12.47 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-070