PJM-AH2-072
62.1 MW storage in Washington, VA · In queue since January 2022 · Proposed COD January 2025
62.1 MW
Capacity
1
Components
Battery
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-01
PJM-AH2-072 is a proposed battery storage project located in Washington County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 62.1 MW, consists entirely of battery storage. The interconnecting utility is AEP.
The project entered the PJM interconnection queue on January 21, 2022, with a proposed commercial operation date of January 1, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Damascus 69 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Washington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Damascus 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DAMASCUS230 KV T4
- POI Substation
- Damascus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.