PJM-AH2-075
29.12 MW storage in City Of Hampton, VA · In queue since January 2022 · Proposed COD July 2024
29.12 MW
Capacity
1
Components
Battery
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-01
PJM-AH2-075 is a proposed battery storage project with a total capacity of 29.12 MW. The project is located in the City of Hampton, Virginia, within the PJM Interconnection region. Dominion is the utility. The project entered the PJM queue on January 21, 2022, with a proposed commercial operation date of July 1, 2024.
The interconnection agreement for PJM-AH2-075 is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
City Of Hampton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Hampton VA 2
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-075