PJM-AH2-076
52.5 MW hybrid in Perry, KY · In queue since January 2022 · Proposed COD December 2023
52.5 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 11m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
The proposed PJM-AH2-076 project is a 52.5 MW hybrid solar and battery energy storage development in Perry County, Kentucky. Interconnection to the grid is planned through the Bonneyman - Softshell 138 kV point of interconnection, managed by utility AEP within the PJM Interconnection region.
The project entered the PJM interconnection queue on January 26, 2022, with a proposed commercial operation date of December 31, 2023. The interconnection agreement is currently listed as "In Progress (unknown study)". The project consists of 52.5 MW of solar generation capacity.
Generated from interconnection queue and public data sources
State
KY
County
Perry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Bonneyman - Softshell 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.