PJM-AH2-080
52.65 MW generation in Brunswick, VA · In queue since January 2022 · Proposed COD January 2025
52.65 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-03
PJM-AH2-080 is a proposed solar generation project with a total capacity of 52.65 MW. The project is located in Brunswick County, Virginia, within the PJM Interconnection region. The queue entry date is January 28, 2022, with a proposed commercial operation date of January 3, 2025. Dominion is the interconnecting utility.
The project's interconnection status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Brunswick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Brunswick - Gasburg 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BRUNSWIC26 KV BRUNSWSP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-080