PJM-AH2-082
33.25 MW generation in Fayette, OH · In queue since January 2022 · Proposed COD January 2025
33.25 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-03
PJM-AH2-082 is a proposed solar generation project with a total capacity of 33.25 MW. The project is located in Fayette County, Ohio, and is being developed within the PJM Interconnection region. The project entered the PJM queue on January 27, 2022, with a proposed commercial operation date of January 3, 2025.
The interconnection agreement for PJM-AH2-082 is currently listed as "In Progress (unknown study)". The point of interconnection is the New Holland - Washington Courthouse 69 kV line. The local utility is Dayton.
Generated from interconnection queue and public data sources
State
OH
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
New Holland - Washington Courthouse 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-082