PJM-AH2-083
140 MW storage in Caroline, VA · In queue since January 2022 · Proposed COD June 2027
140 MW
Capacity
1
Components
Battery
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
PJM-AH2-083 is a proposed 140 MW battery storage project located in Caroline County, Virginia. The project is in the PJM interconnection queue as of January 27, 2022, with a proposed commercial operation date of June 1, 2027. Dominion is the utility and the point of interconnection is at Correctional. The interconnection agreement is currently listed as "In Progress (unknown study)".
The development project consists entirely of battery storage, with a total capacity of 140 MW. It is currently listed as an active project within the PJM queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Caroline
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Correctional
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- Livingston Correctional Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.