PJM-AH2-085
145.335 MW generation in Dekalb, IL · In queue since January 2022 · Proposed COD November 2026
145.335 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-11
PJM-AH2-085 is a proposed solar generation project with a total capacity of 145.34 MW. The project is located in Dekalb County, Illinois, within the ComEd service area and the PJM Interconnection region. The project entered the PJM queue on January 28, 2022, and has a proposed commercial operation date of November 11, 2026. Its interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists solely of solar photovoltaic generation. It is currently listed as an active project in the PJM interconnection queue. The point of interconnection is the Byron-Wayne 345 kV line.
Generated from interconnection queue and public data sources
State
IL
County
Dekalb
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Byron-Wayne 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.