PJM-AH2-087
50 MW storage in Ogle, IL · In queue since January 2022 · Proposed COD December 2025
50 MW
Capacity
1
Components
Battery
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 11m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH2-087 is a proposed 50 MW battery storage project located in Ogle County, Illinois. The project is interconnected within the PJM Interconnection queue, with an entry date of January 31, 2022. The proposed commercial operation date is December 31, 2025. The project is currently in the "In Progress (unknown study)" stage for its Interconnection Agreement (IA). The interconnecting utility is ComEd, and the point of interconnection (POI) is the Byron - Wayne 345 kV line.
The development project consists solely of battery storage, with a total capacity of 50 MW. The project is listed as "active" within the PJM queue.
Generated from interconnection queue and public data sources
State
IL
County
Ogle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Byron - Wayne 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-087