PJM-AH2-093
32 MW hybrid in Greene, OH · In queue since January 2022 · Proposed COD December 2025
32 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 11m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed project PJM-AH2-093 is a 32 MW hybrid solar and battery energy storage project located in Greene County, Ohio. The project consists of 32 MW of solar generation. It is interconnected within the PJM Interconnection queue, having entered the queue on January 31, 2022, with a proposed commercial operation date of December 31, 2025. The point of interconnection is the Jasper 69 kV substation.
The interconnection agreement for PJM-AH2-093 is currently listed as "In Progress (unknown study)". The utility involved is Dayton.
Generated from interconnection queue and public data sources
State
OH
County
Greene
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Jasper 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-093