PJM-AH2-094
4.95 MW generation in Wayne, PA · In queue since January 2022 · Proposed COD May 2023
4.95 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 4m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-05
The proposed project PJM-AH2-094 is a 4.95 MW solar generation project located in Wayne County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, with an initial queue entry date of January 31, 2022. The proposed commercial operation date is May 5, 2023.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The interconnecting utility is PPL, and the point of interconnection (POI) is Lakeville 12 kV II. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Wayne
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Lakeville 12 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PAUPACK 69 KV HONE1
- POI Substation
- Lakeville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.