PJM-AH2-095
3.3 MW generation in Crawford, PA · In queue since January 2022 · Proposed COD July 2022
3.3 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
6 months
Schedule
46 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-07-13
PJM-AH2-095 is a proposed 3.3 MW solar generation project located in Crawford County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on January 31, 2022. The proposed commercial operation date is July 13, 2022.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Crawford 13.8 kV substation. The utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Crawford 13.8 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.