PJM-AH2-100
20 MW generation in Prince Edward, VA · In queue since January 2022 · Proposed COD December 2023
20 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 11m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-29
PJM-AH2-100 is a proposed 20 MW solar generation project located in Prince Edward County, Virginia. The project is in the PJM interconnection queue, with an entry date of January 31, 2022, and a proposed commercial operation date of December 29, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
Dominion is the utility associated with the project. The point of interconnection is the Briery Substation at 29.4kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
VA
County
Prince Edward
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Briery Substation 29.4kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-100