PJM-AH2-102
200 MW storage in Franklin, VA · In queue since January 2022 · Proposed COD May 2026
200 MW
Capacity
1
Components
Battery
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-04
PJM-AH2-102 is a proposed 200 MW battery storage project located in Franklin County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on January 31, 2022. The proposed commercial operation date is May 4, 2026. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project, which is being developed within the AEP service territory, consists solely of battery storage. It is interconnected at the Blaine - Roanoke 138 kV point of interconnection. The project has appeared in recent news coverage regarding energy storage development in the PJM region.
Generated from interconnection queue and public data sources
State
VA
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Blaine - Roanoke 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-102