PJM-AH2-104
72 MW hybrid in Cumberland, VA · In queue since February 2022 · Proposed COD November 2024
72 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 9m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-01
The proposed project PJM-AH2-104 is a 72 MW solar and battery hybrid development located in Cumberland County, Virginia. Interconnecting within the PJM Interconnection queue under utility Dominion, the project entered the queue on February 4, 2022, and has a proposed commercial operation date of November 1, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".
The project consists of 72 MW of solar generation capacity. It is listed as an active project in the PJM queue.
Generated from interconnection queue and public data sources
State
VA
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Willis Mts- Farmville 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.