PJM-AH2-107
69 MW storage in City Of Suffolk, VA · In queue since February 2022 · Proposed COD December 2024
69 MW
Capacity
1
Components
Battery
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 10m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH2-107 is a proposed 69 MW battery storage project located in the City of Suffolk, Virginia. The project is in the PJM interconnection queue, with an entry date of February 12, 2022, and a proposed commercial operation date of December 31, 2024. Dominion is the interconnecting utility.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
City Of Suffolk
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Suffolk 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SUFFOLK 35 KV SUFFLKSP
- POI Substation
- Suffolk Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-107