PJM-AH2-109
1.5 MW generation in NJ · In queue since February 2022 · Proposed COD December 2022
1.5 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
10 months
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
PJM-AH2-109 is a proposed solar generation project with a total capacity of 1.5 MW, located in New Jersey within the PJM Interconnection region. The project, which entered the PJM queue on February 16, 2022, is being developed by an unknown entity and is planned to interconnect with AEC at the TBD 12.47kV point of interconnection. The proposed commercial operation date is December 1, 2022.
The project's interconnection status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
NJ
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
TBD 12.47kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM