85 MW generation in Cambria, PA · In queue since February 2022 · Proposed COD January 2026
85 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 11m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PJM-AH2-116 is a proposed solar generation project with a total capacity of 85 MW, located in Cambria County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 23, 2022, with a proposed commercial operation date of January 1, 2026. The interconnection agreement is currently listed as "In Progress (unknown study)".
The proposed project, which will connect to the PENELEC utility grid at the Garman - Westover South 115 kV point of interconnection, consists solely of 85 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
PA
County
Cambria
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Garman - Westover South 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.