PJM-AH2-119
15 MW generation in Crawford, PA · In queue since February 2022 · Proposed COD December 2025
15 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-30
PJM-AH2-119 is a proposed solar generation project with a total capacity of 15 MW, located in Crawford County, Pennsylvania. The project is in the PJM interconnection queue, with an entry date of February 25, 2022, and a proposed commercial operation date of December 30, 2025. The interconnecting utility is PENELEC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Morgan Street - Titusville 34.5 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Morgan Street - Titusville 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-119