PJM-AH2-125
100 MW storage in KY · In queue since February 2022 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
PJM-AH2-125 is a proposed 100 MW battery storage project located in Kentucky. The project, which consists of a 100 MW battery component, is in the PJM interconnection queue as of February 26, 2022, with a proposed commercial operation date of December 1, 2028. The interconnection agreement is currently listed as "In Progress (unknown study)".
The project's point of interconnection (POI) is Kensington 138 kV. The queue ID is PJM-AH2-125.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kensington 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Kensington Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-125