PJM-AH2-127
18 MW storage in Burlington, NJ · In queue since February 2022 · Proposed COD September 2023
18 MW
Capacity
1
Components
Battery
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 7m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-19
PJM-AH2-127 is a proposed 18 MW battery storage project located in Burlington County, New Jersey. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 25, 2022. The proposed commercial operation date is September 19, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The project, which is being developed within the Public Service Electric and Gas (PSEG) service area, consists solely of battery storage with a total capacity of 18 MW.
Generated from interconnection queue and public data sources
State
NJ
County
Burlington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
—
Point of Interconnection
Burlington 26 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BURLING2138 KV T1
- POI Substation
- Burlington Heights Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-127