PJM-AH2-137
10 MW generation in Amherst, VA · In queue since February 2022 · Proposed COD December 2026
10 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PJM-AH2-137 is a proposed solar generation project located in Amherst County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 10 MW, consists entirely of solar photovoltaic generation. Its interconnection request was entered into the PJM queue on February 28, 2022, with a proposed commercial operation date of December 1, 2026. The interconnection agreement is currently listed as "In Progress (unknown study)".
The proposed project is located within the service territory of utility AEP. The point of interconnection is the Monroe - Coolwell 12.47 kV line. The project's status is currently listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
Amherst
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Monroe - Coolwell 12.47 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM