Project PJM-AH2-137 — Project Summary

Queue ID
PJM-AH2-137
Capacity
10 MW
Technology
Solar
Status
active
Location
Amherst, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH2-137

PJM-AH2-137BetaActiveSolarPJMLBNL + Live

10 MW generation in Amherst, VA · In queue since February 2022 · Proposed COD December 2026

10 MW

Capacity

1

Components

Solar

4y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection

Total Duration

4y 10m

In Study38%
Queue EntryFeb 28, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

About

PJM-AH2-137 is a proposed solar generation project located in Amherst County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 10 MW, consists entirely of solar photovoltaic generation. Its interconnection request was entered into the PJM queue on February 28, 2022, with a proposed commercial operation date of December 1, 2026. The interconnection agreement is currently listed as "In Progress (unknown study)".

The proposed project is located within the service territory of utility AEP. The point of interconnection is the Monroe - Coolwell 12.47 kV line. The project's status is currently listed as active within the PJM interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Amherst

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Monroe - Coolwell 12.47 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH2-137