PJM-AH2-146
87.2 MW hybrid in Adams, OH · In queue since February 2022 · Proposed COD December 2027
87.2 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-30
PJM-AH2-146 is a proposed 87.2 MW hybrid solar and battery project located in Adams County, Ohio. The project, which consists of 87.2 MW of solar capacity, is in the PJM interconnection queue as of February 28, 2022, with a proposed commercial operation date of December 30, 2027. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Adams - Seaman 69 kV line. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
OH
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Adams - Seaman 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.