PJM-AH2-151
35 MW hybrid in Halifax, VA · In queue since February 2022 · Proposed COD June 2025
35 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
PJM-AH2-151 is a proposed 35 MW hybrid Solar+Battery project located in Halifax County, Virginia. The project is in the PJM interconnection queue, with an entry date of February 28, 2022, and a proposed commercial operation date of June 1, 2025. Dominion is the interconnecting utility.
The project consists of 35 MW of solar generation. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the SedgeHill - Person 230kV line. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
SedgeHill - Person 230kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.