PJM-AH2-157
12 MW generation in Somerset, PA · In queue since March 2022 · Proposed COD December 2025
12 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH2-157 is a proposed solar generation project with a total capacity of 12 MW, located in Somerset County, Pennsylvania. The project is in the PJM interconnection queue as of March 2, 2022, with a proposed commercial operation date of December 31, 2025. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility territory. The point of interconnection is the Hooversville-Somerset 23 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Hooversville-Somerset 23 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-157