PJM-AH2-159
49 MW generation in Highland, OH · In queue since March 2022 · Proposed COD December 2025
49 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH2-159 is a proposed solar generation project with a total capacity of 49 MW, located in Highland County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 2, 2022. The proposed commercial operation date is December 31, 2025. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Buckskin _x0013_ Worley 69 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Highland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Buckskin _x0013_ Worley 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-159