PJM-AH2-163
19.8 MW generation in Armstrong, PA · In queue since March 2022 · Proposed COD March 2026
19.8 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
PJM-AH2-163 is a proposed solar generation project with a total capacity of 19.8 MW. The project is located in Armstrong County, Pennsylvania, and is interconnected within the PJM Interconnection region, with APS as the interconnecting utility. The project entered the PJM queue on March 4, 2022, and has a proposed commercial operation date of March 1, 2026.
The interconnection agreement for PJM-AH2-163 is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
Armstrong
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Kittanning - Rural Valley 25 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VALLEY4 230 KV SR_1