PJM-AH2-164
85 MW generation in Crawford, OH · In queue since March 2022 · Proposed COD January 2026
85 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PJM-AH2-164 is a proposed solar generation project located in Crawford County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 85 MW, consists entirely of solar photovoltaic technology. The queue entry date for interconnection is March 4, 2022, with a proposed commercial operation date of January 1, 2026. The interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP.
The proposed project is listed in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
OH
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Chatfield 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RONCO 18 KV CT2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-164