PJM-AH2-168
185 MW generation in Madison, OH · In queue since March 2022 · Proposed COD December 2025
185 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH2-168 is a proposed solar generation project with a total capacity of 185 MW. The project is located in Madison County, Ohio, within the PJM Interconnection region and is being managed by utility ATSI. The project entered the PJM queue on March 8, 2022, with a proposed commercial operation date of December 31, 2025.
The interconnection agreement for PJM-AH2-168 is currently listed as "In Progress (unknown study)". The point of interconnection is the Beatty - MT Hope 345 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Madison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Beatty - MT Hope 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.