PJM-AH2-190
12 MW generation in Somerset, PA · In queue since March 2022 · Proposed COD December 2025
12 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH2-190 is a proposed solar generation project located in Somerset County, Pennsylvania. The project, with a total capacity of 12 MW, is interconnected within the PJM Interconnection queue. The queue entry date is March 9, 2022, and the proposed commercial operation date is December 31, 2025. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The project consists of 12 MW of solar photovoltaic generation. The designated point of interconnection (POI) is Higgins Run Solar. The utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Higgins Run Solar
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-190