PJM-AH2-194
20 MW generation in Bergen, NJ · In queue since March 2022 · Proposed COD April 2026
20 MW
Capacity
1
Components
Gas
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-30
The proposed project PJM-AH2-194 is a 20 MW natural gas generation project located in Bergen County, New Jersey. The project is in the PJM interconnection queue as of March 9, 2022, with a proposed commercial operation date of April 30, 2026. The interconnecting utility is PSEG.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Bergen 138kV substation.
Generated from interconnection queue and public data sources
State
NJ
County
Bergen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
—
Point of Interconnection
Bergen 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HCS 500 KV NYPUMP
- POI Substation
- North Bergen Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.