PJM-AH2-195
65 MW generation in Indiana, PA · In queue since March 2022 · Proposed COD October 2027
65 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-29
PJM-AH2-195 is a proposed solar generation project with a total capacity of 65 MW, located in Indiana County, Pennsylvania. The project is in the PJM interconnection queue as of March 8, 2022, with a proposed commercial operation date of October 29, 2027. The interconnection agreement is currently in progress, with the specific study phase unknown. The point of interconnection is the Seward-Glory 115 kV line.
The development project is located within the PENELEC utility service area. The project consists of 65 MW of solar photovoltaic generation. The project's status is currently listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Indiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Seward-Glory 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM