PJM-AH2-197
50 MW hybrid in Mchenry, IL · In queue since March 2022 · Proposed COD December 2025
50 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed project PJM-AH2-197 is a 50 MW solar and battery hybrid development in Mchenry County, Illinois. Interconnection is with ComEd via the North Huntley - Pleasant Valley 138 kV point of interconnection. The project consists of 50 MW of solar capacity.
The project is in the PJM interconnection queue with an entry date of March 8, 2022, and a proposed commercial operation date of December 31, 2025. The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
IL
County
Mchenry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
North Huntley - Pleasant Valley 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VALLEY4 230 KV SR_1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.