PJM-AH2-206
10 MW storage in Cook, IL · In queue since March 2022 · Proposed COD March 2026
10 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-31
The proposed energy storage project PJM-AH2-206 is a 10 MW battery development in Cook County, Illinois. The project is located within the PJM Interconnection region and is being managed by utility ComEd.
The project entered the PJM queue on March 9, 2022, with a proposed commercial operation date of March 31, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is I.C. Air Rights 12.5 kV.
Generated from interconnection queue and public data sources
State
IL
County
Cook
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
I.C. Air Rights 12.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-206